273
Councillor Bentley declared a non-pecuniary interest in
this item by virtue of his role as Leader of Essex County Council, and the information
presented in relation to the Shrub End Depot project.
Paul Cook, Head of Finance, attended the meeting to present
the report and assist the Committee with its enquires. The Committee heard that
capital expenditure had been £7.7m against a forecast programme of £84.7m,
which represented an expenditure of 9% of the projected budget. This
represented a slow start which was attributable to the labour and supply issues
experienced as a result of the pandemic and represented a similar position to
the last financial year. Careful monitoring would be required in quarters three
and four to ensure that progress was delivered. The attention of the Committee
was drawn to the schedule of projects set out in the report, each of which was
attributed a red, amber or green (RAG) rating, with explanations for the rating
provided.
Rosa Tanfield, Group Manager – Neighbourhood Services,
attended the meeting to provide the Committee with an update on the Shrub End
Depot project. The Committee heard that after a faltering start to the project,
good progress was now being made, with changes being made to the site to
improve things for staff as well as variety of works to ensure safety. In the
coming weeks work would be undertaken which would include the provision of a
new crew shelter, car park improvements, new fencing and drainage works. Work
was continuing with design work on the larger elements of the project which
would go to tender to determine the overall costs of the project. Although good
progress was being made in all areas, the Committee were reminded that as with
all construction projects there remained some risks in relation to budget and
timeline and in particular material availability. The Committee were assured
that the project was the subject of close monitoring to ensure that value for
money was obtained, and overall good progress was being made.
Councillor Willetts acknowledged the need for short term
work to be carried out on the Shrub End site to improve facilities for staff to
make it a safer and more comfortable site to work from. He noted that Essex
County Council were considering a waste transfer station at Ardleigh, and sought
assurances that the improvement works currently being carried out at Shrub End
were necessary short term modifications and that the longer term plan would be
to align with Essex County Council to ensure that improvements had value in the
future.
Rosa Tanfield confirmed that the current works represented
a short to medium term series of improvements which were targeted to meet the
immediate needs of staff, and that wherever possible consideration was given to
improvements made which could be adapted or moved if there was any change to
the site in the future. The longer term position of the site had yet to be
explored, and there were a number of things to consider including not only the
recycling and refuse operation but also the Council’s ambition to move to an
electric vehicle (EV) fleet and the infrastructure needed to support this. The
Environment Bill was also likely to have far reaching implications for the
site, and all these factors needed to be given careful consideration to ensure
that any changes that were made represented good value for money.
Councillor Lissimore, Portfolio Holder for Resources, assured
the Committee that there was no intention to spend money on a site that was
going to be scrapped, and of key importance was the fact that the project could
be moved in the future if need be. The works that were being carried out would
bring significant improvements to staff in the short term, and discussions had
taken place with the Cabinet Member for Waste and Environment of Essex County
Council with a view to establishing the long term future of the site to ensure
that the best use was made of it.
Councillor King praised the work that was being undertaken
to adapt the site to the current circumstances, and although he noted that the project
had taken a while to get off the ground he offered his full support to the
project and was very pleased that it was taking place. Greater communications
with Essex County Council were welcomed, however, he stressed that working with
the County Council should not come at the detriment of the excellent waste
collection and recycling services currently being provided by the Council.
Councillor Willetts advised the Committee that action that
was taken on the Shrub End site would be the subject of a Cabinet decision, and
the paper that had been presented to the Committee was for their information,
and to note only.
Councillor Fox enquired what the potential of labour
shortages and supply issues was for causing difficulties with the capital
budget, and whether any specific work had been carried out on the risk of
inflationary pressures in the budget causing some of the capital projects to go
over budget or become undeliverable.
Paul Cook confirmed that the Council was aware of inflation
supply risks, and although some projects had already been tendered, this was
something that would be considered carefully in the future. There would be a
comprehensive review of the capital budget when setting the budget for the
financial year 2022/2023. In response to a further question from Councillor Fox
in relation to house prices associated with Council capital housing projects,
the Committee heard that if a significant cost variation was identified then
this would be reported to Cabinet.
Councillor Willetts noted that a comprehensive review had
been carried out of the capital programme and wondered whether or not the
difficulties currently being experienced in the building trade with regard to the
supply and cost of materials had been factored into the project RAG ratings. Paul
Cook advised the Committee that as far as possible all these factors had been
considered, and that at the start of the financial year it had not been certain
that progress would be able to be made on capital projects at all, but
thankfully the position had improved since then. More detailed analysis would
be provided as part of the quarter two monitoring report presented to the
Committee.
Councillor Bentley suggested that capital projects should
be accompanied by a risk register in order to monitor the impact that external
factors could have on projects to ensure clarity for the public. He noted that
the Stanway Community Centre project had a shortfall of money, and he wondered
what confidence there was that the shortfall could be made up, and from where.
Paul Cook confirmed that when projects were brought into
the capital programme, funding assumptions were made in order to calculate the
budget but that these assumptions were subject to change and would be picked up
at the next review. With regard to risks, the Committee were advised that the
Council took a corporate approach to risk management and it was essential that a
balanced approach be adopted to any risk reporting associated with capital
projects. Further consideration could be given to risk management as part of
the next monitoring report.
Councillor King considered that it was important to
understand the pressures that were being faced, and how these fitted into budgetary
position. When considering the RAG ratings for the capital programme,
Councillor King felt that the number of red and amber rated projects could be
cause for alarm, and he sought assurance that there was confidence that the
programme would be able to be delivered, with more information on risk and
contingency presented to the Committee in the future.
By way of response, Dan Gascoyne gave his opinion that the
number of red and amber RAG ratings assigned to projects was not cause for
alarm, but rather evidence of clear analysis and transparency when considering
projects. The Committee were reminded that the report only dealt with quarter
one, and that more detailed updates would be expected as the year unfolded.
Assurance was given that the programme was carefully monitored by the Council’s
Senior Management Team and Officers, and all the risks associated with projects
were being actively managed.
Councillor Willetts noted the difficulty that had been
experienced with the procurement of vehicles for the Council’s fleet to replace
and upgrade existing vehicles, and he wondered if an opportunity had presented
itself to re-tender for vehicles which were not powered by internal combustion
engines, but rather by electric or hydrogen engines, and which would therefore support
the Council’s own climate emergency declaration. Dan Gascoyne confirmed that
the schemes which had been referred to were consistent with the Council’s fleet
transition strategy which would deliver carbon neutrality by 2030. Although
there may be an opportunity to re-tender with different contract
specifications, the delays that this may incur could lead to additional
expense. Rosa Tanfield confirmed to the Committee that since the report had
been published, significant progress had been made with regard to the
procurement of caged tipper vehicles, and this project was now moving towards a
green RAG rating. The other project that had been referred to by Councillor
Willetts was light fleet replacement, which was concerned with the procurement
of electric vehicles (EV) which the first step to bringing in an EV fleet,
together with the necessary infrastructure to support this.
RESOLVED: that the contents of
the report be noted.