496
The Committee considered a report which requested that it approve the 2023/24
statement of accounts, noting the 2023/24 Audit Plan, Letter of Representation to be
signed by the S151 Officer and two audit reports: the Year-End Report to the
Governance and Audit Committee (ISA 260 report), and the Auditors’ Annual Report;
and that it noted and approved the Annual Governance Statement, to be signed by
the Leader of the Council and the Chief Executive; and that it noted and agreed the
Audit Plan for 2024/25.
Before the item had been presented, the Chair pointed out that the documents which
were before the Committee made reference to papers having been presented to the
Committee in March 2025, whereas in fact these documents were being presented
at the current meeting.
Emma Larcombe, Director, KPMG, attended the meeting to present the report and
assist the Committee with its enquiries. A large number of documents were before
the Committee, some of which were required to be included as a formality, and the
attention of the Committee was drawn to a number of these.
The Audit Plan for the 2023/2024 accounts had been included, and under normal
circumstances this would have been presented to the Committee during the
preceding year, however, it had not been possible to do this. The Audit Plan was
required to be presented to the Committee, and was therefore included in the
paperwork which was before it.
The Management Representation Letter was a standard representation letter which
stated the various representations which the Interim S151 Officer would confirm in
terms of the preparation of those accounts. No specific representations had been
made, and no adjustments had been made for the fact that the audit opinion was
disclaimed.
KPMG’s Year End Summary Report was also before the Committee, and this set out
the current position in terms of the backstop for the completion of the accounts,
which, as the Committee had been aware, had been the end of February 2025. It
had not been possible to meet this backstop date as the accounts had not been
finalised by this point. A fully disclaimed audit opinion had been issued for the
2023/2024 accounts as KPMG had been unable to complete any audit work other
than basic planning procedures. Additionally, a review of the accounts had been
carried out which had identified significant numbers of casting errors, all of which had
been addressed promptly by the Council’s Finance Team. KPMG were now
comfortable with the set of accounts which would be signed off.
A number of areas had been identified as the result of the work which KPMG had
carried out, including the capacity and capability within the Council’s Finance Team,
which the Interim S151 Officer had already taken steps to address, and there had
already been a significant change in the amount of work which KPMG had been able
to accomplish towards the 2024/2025 audit. Another issue which had been identified
was around local counter fraud measures, however, the Director, KPMG had every
faith that this would be addressed during the forthcoming financial year due to the
changes within the Finance Team.
The Committee was directed towards the section of the report which dealt with the
reset and recovery phase for local authority accounting, which provided a useful
guide on what the Council should expect for the preparation of its accounts in the
forthcoming years culminating in an unmodified audit opinion.
The report confirmed KPMG’s independence as the Council’s auditors, and the fee
which was payable by the Council would be confirmed through the Public Sector
Audit Appointments (PSAA)’s process.
Anna D’Alessandro, Interim S151 Officer, attended the meeting and assured the
Committee that she had taken the auditors recommendations seriously and had
taken immediate steps to strengthen the Council’s Finance Team. KPMG had been
supportive and enjoyed a good relationship with the Council which was of critical
importance.
A Committee member considered that the information which had been provided in
relation to the local authority audit reset was very comprehensive and clear, and he
considered that the Council would be in a strong position with a robust financial basis
going into local government reorganisation (LGR). He understood that attaining
confidence in the opening balance would take a number of years. He noted that
KPMG had issued a disclaimer, and the Committee was being asked to approve and
publish the accounts. In dealing with the preceding 3 years of accounts, the
Committee had agreed to modify its recommended decision to provide some
protection to Committee members who were agreeing a disclaimed set of accounts
and who worked in the finance industry. A suggested modified recommendation had
been circulated to the Committee ahead of the meeting, and the wording of this was
read to the Committee;
“The Committee is Recommended to:
2.1 The Committee approves the publication of the 2023/24 statement of accounts,
noting the 2023/24 Audit Plan, Letter of Representation to be signed by the S151
Officer and the two audit reports: the Year-End Report to the Governance and Audit
Committee (ISA 260 report), and the Auditors’ Annual Report (similar content but
designed for a wider audience including the public) but the Governance and Audit
Committee acknowledges that the external auditors have issued a disclaimer of
opinion on the Council’s Statement of Accounts for the year ended 31 March 2024.
This was because they were unable to obtain sufficient appropriate audit evidence to
provide a basis for an audit opinion.
The Committee has considered the circumstances that led to the disclaimer and
notes the shortcomings identified by the auditors. While recognising the potential for
material misstatement, the Committee has approved the accounts for publication in
accordance with statutory requirements.
The Committee supports the ongoing programme of improvements to address the
issues raised by the auditors, and is committed to ensuring timely and accurate
financial reporting in future years.
2.2 Note and approve the Annual Governance Statement, to be signed by the
Leader of the Council and the Chief Executive;
2.3 Note and agree the Audit Plan for 2024/25”
This suggested revised recommended decision should also be noted in the accounts
themselves to provide a record of what the Committee had resolved.
A Committee member proposed an amendment to the suggested revised
recommendation which was the insertion of the words “historic situation and” before
the word “shortcomings” in the second paragraph. This suggestion was accepted.
The Chair made reference to the stance which the Committee had previously taken
when it had agreed to the publication of the preceding 3 years of accounts which had
included a disclaimer from the Committee. The Council’s previous auditors, BDO,
had indicated that they would not consent to an additional statement being added to
the statement of accounts, were KPMG happy with the addition of such a statement
to this set of accounts? The minutes of the meeting in December 2024 had placed
on record the concerns of the Committee, so that members of the public could
understand and appreciate these.
The Director, KPMG indicated that she was relatively comfortable that the proposed
form of words was reasonable. On balance, she would prefer that the form of words
was published as the recommendation from the Committee, however, what was of
greater importance was the Annual Governance Statement (AGS), which
acknowledged the issues which had been identified which had led to the current
situation with the Council’s accounts.
A Committee member stated that he was passionately determined that the resolution
of the Committee should be added in to the statement of accounts as part of the
statement of the Council’s responsibilities. In his opinion, the Committee had to say
very clearly that it was not approving the accounts, due to the errors which had been
identified in them, without proper qualification and explanation. The accounts were
those of the Council, and not the auditors, and in the light of the disclaimed audit
report it was important that the accounts were modified to clearly show the
reservations of the Committee.
The Committee discussed the points which had been made, and was pleased to
note that there had been a noticeable improvement in the Council’s engagement with
KPMG. Although it understood the stance of the Director, KPMG, it was suggested
that if it could be accepted, albeit reluctantly, that the proposed wording be entered
into the accounts, then the Committee would support this. A Committee member
indicated that he would not support the inclusion of the statement into the accounts
as he felt that this may jeopardise the good relationship which was being built with
the auditors.
Following a brief adjournment, the Committee was advised that it had been agreed
with KPMG that the words from its recommendation would be inserted into the
accounts on a page of their own at page 28. This compromise was acceptable to
both the Council’s auditors and to the Interim S151 Officer.
A Committee member did not approve of this suggestion, and proposed that the
Committee treat this set of accounts in the same way it had treated the preceding 3
years of accounts by recording the Committee’s decision in the minutes of the
meeting, and he wished to amend the suggested wording to this effect. The
Committee voted on the proposed amendment which was lost.
The Director, KPMG, reiterated to the Committee that casting errors which had been
identified in the accounts had been corrected, and the set of accounts which would
be approved did not contain any further errors.
Turning to the Value For Money (VFM) element of the auditor’s report, it was
confirmed to the Committee that KPMG had carried out the full suite of VFM work,
and the Committee received an overview of what this work entailed. Areas of risk
had been identified as being;
- Risk management procedures were considered to be a risk in the VFM
arrangements, but were not indicative of an overall weakness. Management
had accepted the recommendation in this area.
- Fraud Risk Management had already been mentioned during the meeting,
and management had accepted the recommendation which had been made.
- Governance in relation to financial reporting, which was being addressed by
the Interim S151 Officer.
- Oversight of Council assets had been identified as a weakness in
arrangements due to the lack of implementation of recommendations which
had been made to the Council as part of a CIPFA review.
- The capability and capacity of the Council’s Finance Team had been accepted
as a weakness, and steps had been taken to address this.
- Procurement and contract management had been identified as a risk following
internal audit reviews. No significant weakness had been raised in this area
due to the processes which had been undertaken to track, report and monitor
this risk.
- Challenges associated with the Northern Gateway development had been
identified, and although no significant weakness had been identified in this
area, progress did need to be made.
All the recommendations which had been made had been accepted by the Council’s
management and were also reflected in the AGS for 2023/2024.
In terms of the Northern Gateway project, as this was a large, ongoing project, it
would be considered during the forthcoming financial year to ensure that any issues
which arose were reported, and risks identified.
A Committee member hoped that a project risk register would be developed, which
would feature the Northern Gateway development. He believed that this
development would eventually need to be recognised on the Council’s balance
sheet, had a note on this subject been included in the 2023/2024 accounts? The
Interim S151 Officer confirmed that full disclosure around the Northern Gateway
development would be dealt with in the 2024/2025 accounts, and a contingent
liability in relation to the development had been included in the 2023/2024 accounts.
A Committee member raised a number of questions in respect of the fees of KPMG
which had been set out in the report. Why had 2 different fee schedules been
provided, and why were the fees of KPMG so much higher than those of the
Council’s previous auditors, BDO? Additionally, risks had been identified which may
affect the fees which were charged in the future, however, these risks were historic in
nature and could no longer be addressed. What, therefore, would be the penalty to
the Council if historic risks materialised and impacted on the work which was
required and the fees charged?
The Director, KPMG, confirmed that the fees of £160,000 listed in the first table
would be charged for the current year. The scale rate fee which KPMG were entitled
to charge for a full audit was £189,000 for a full audit, however, this had been
reduced as a full audit had not been completed, before fee variations relating to
areas of work which had taken longer to complete, including the issuing of a
disclaimer, had been added, bringing the total fee back up to £160,000. The fees
which were charged by auditors were the new scales fees set by the PSAA, following
a tender process, and auditors had no influence over these. All fee variations had to
be approved by the PSAA. In terms of the risks which had been identified which
were associated with the 2023/2024 accounts, further work would be carried out in
relation to these as they had been identified as areas of weakness, however, KPMG
now had a good understanding of the authority and although additional fees would
be payable for the further VFM work which was required, it was not expected that
this additional work would cause the fees to be significantly higher.
Hannah Lincoln, Senior Manager, KPMG, attended the meeting and addressed the
Committee with respect to the 2024/2025 Audit Plan. Key risks had been identified in
the Plan, and related to valuation of land and buildings and the valuation of
investment properties, which was an area which would be checked by a specialist
valuations team. Additionally standard risks such as management override of
controls would also be reviewed. There had been 2 risks identified in relation
pensions, the valuation of the obligations and the recognition of surplus on the net
pension asset, and a specialist pensions team would be involved in this work as
KPMG would not solely rely on the work which had been carried out by ECC but
would test the specific work which was done for the Colchester notes. The final risk
which had been identified was expenditure recognition.
There was a backstop date for the completion of the 2024/2025 accounts which was
the end of February 2026, and it was hoped that the necessary field work would be
concluded prior to the end of 2025, allowing additional work to be carried out prior to
the backstop date to rebuild assurance from previous years.
A Committee member noted a figure that that the Council had utilised 22% of its
usable reserves to support a balanced budget, and found this figure concerning. Was
it possible to provide some context around this figure, and was any benchmarking
from other local authorities available in this area?
The Senior Manager, KPMG, confirmed that over the preceding 4 years there had
been a significant increase in the use of reserves, but this was now coming back to a
more normal level following the disruption which had been caused by the covid-19
pandemic. This area would be subject to audit, but was not considered to be a key
area of concern. Very little benchmarking data was available at the present time,
however, the provision of such data would be considered in the future as it became
available.
Noting the impact that variations in interest rates had on the Council’s pension
surplus or liability, the Committee sought to understand how this would be reflected
in the accounts. The Director, KPMG, confirmed that the recognition of a surplus
asset was subject to a large number of criteria, and KMPG had a specialist team
which had extensive experience in auditing local government pension schemes.
RESOLVED that:
- The publication of the 2023/24 statement of accounts be approved, and the
2023/24 Audit Plan, Letter of Representation be signed by the S151 Officer
and the two audit reports: the Year-End Report to the Governance and Audit
Committee (ISA 260 report), and the Auditors’ Annual Report (similar content
but designed for a wider audience including the public) be noted, but the
Governance and Audit Committee acknowledged that the external auditors
had issued a disclaimer of opinion on the Council’s Statement of Accounts for
the year ended 31 March 2024. This was because they were unable to obtain
sufficient appropriate audit evidence to provide a basis for an audit opinion.
- The Governance and Audit Committee considered the circumstances that led
to the disclaimer and noted the historic situation and shortcomings identified
by the auditors. While recognising the potential for material misstatement, the
Committee approved the accounts for publication in accordance with statutory
requirements. The Committee supported the ongoing programme of
improvements to address the issues raised by the auditors, and was
committed to ensuring timely and accurate financial reporting in future years.
- The Annual Governance Statement, to be signed by the Leader of the Council
and the Chief Executive, be noted and approved;
- The Audit Plan for 2024/25 be noted and agreed.
- The wording of this decision be inserted into the 2023/24 statement of
accounts at page 28.