504
Councillor David King, Leader of the Council, introduced the update on works carried out on Town Deal and Levelling Up Fund [LUF] projects during 2024-25. Some had already been delivered whilst others were maturing. Some, such as the Heart of Greenstead [HoG] project were aimed at improvements in some of the most deprived parts of Colchester. The projects were planned to enrich the City’s legacy.
Whilst Scrutiny Panel conducted examination of the project work, oversight was also provided by the Town Deal Board, as mandated by Government. Town Deal and LUF projects both received cross-party scrutiny on matters such as delivery on investment, performance against scheduling and other related issues. A presentation was given, showing the main aspects of each project, work carried out and planned, and main risks associated with the programme.
Lindsay Barker, Deputy Chief Executive, explained that projected costs had first been estimated prior to the Pandemic, and so had seen increases due to cost escalations. The Council worked with a wide range of partners, including significant community involvement in HoG. The Town Deal Board provided close oversight of governance and delivery. The HoG project was described as a hub for community services and a provider of affordable housing with an increase in capacity of the local GP surgery. The project sought to increase modal shift in transport methods, towards walking and cycling. Designs had been revisited, leading to a campus approach for bringing together different services and organisations in one place.
Matt Sterling, Head of Economic Growth, outlined the city centre projects. There were three public realm projects and two heritage projects within the area. The public realm projects were St Nicholas Square, Holy Trinity Church/Trinity Square, and Lexden Gardens [formerly the County Hospital].
Holy Trinity Church had received Town Deal funding for repair works. Lottery funding was then bid for, which would be used to fit out the building to make it suitable for contemporary use. Phase two of the Jumbo/Balkerne Gate project was described, again with Town Deal funding used for repairs, and Heritage Lottery funding to pay for feasibility work to turn Jumbo into a visitor and community facility. £8m Lottery funding has been secured by North Essex Heritage for Jumbo.
Projects for youth facility improvements were centred around the Stanway and Highwoods Centres, and the Town House in the Dutch Quarter. The former two projects had now been completed, whilst the Town House project had been delayed by a necessary retendering of the contract. An appropriate contractor had now been appointed with works to start in the summer.
Physical connectivity work was focussed on improving and increasing walking and cycling links to the city centre. Around three kilometres of new or enhanced routes were planned, including on the route from East Hill to the University.
Digital connectivity projects encompassed a new Digital Forum at 43 Queen Street, a digital skills hub at the Wilson Marriage Centre, and two 5G pilots for the city centre. Building was underway for the Digital Forum, and Colbea were set to run this once operational. June completion was expected. The digital skills hub was complete, having opened in September 2023. The 5G pilots involved infrastructure to test schemes aimed at increasing private investment and to improve the experience of visitors to heritage and museum assets such as the Castle.
Key risks were outlined, with two ‘projects rated as ‘red’ due to matters relating to scheduling and money. All projects were however on track for completion on time and to budget. Constant work was however necessary to keep them on track, with all projects being managed using an Agile project management methodology. The Ministry of Housing, Communities and Local Government [MHCLG] had expressed confidence in project deliverability, which was not always the case in other areas which had won funding. Safer Streets funding was also being pursued, to further augment the work possible on the cycling scheme.
The Panel asked how confident officers were of meeting deadlines. The Deputy Chief Executive acknowledged the consistent challenges to deadlines, giving assurance that there was significant confidence that the contractual requirements would be met by March 2026.
Officers were asked why funding was being given to the Lexden Gardens site [formerly the County Hospital], given that it was not owned by the Council, and why Holy Trinity Church was being set for a charity to run its operation. More information on cost inflation issues regarding street and connectivity work was also requested. The Head of Economic Growth explained that the funding for Lexden Gardens was to enable public use of the residential scheme creating green space on that access to the city centre. The Head of Economic Growth explained that it had always been planned for a third party to run Holy Trinity Church, and that St Helena Hospice were committed to the heritage of the building and to maximise its use. The Deputy Chief Executive underlined that Heritage Lottery funding had included a requirement that the Council worked with a third party to run the Church site.
The Leader of the Council pointed out the exceptional circumstances that had affected the St Nicholas Square project. The Council had learned from these experiences. The Council and its partners continued to experience pressure, but the Leader expressed confidence that officers were on top of the situation.
The Panel asked queries regarding the contingency funding for each project, and whether the project work was operating within these. The Deputy Chief Executive confirmed that this was the case at present time. Some projects had been decommissioned, and the funds assigned to other schemes. MHCLG had accepted the need for this action to be taken. Some risk remained around the Heart of Greenstead project and would do so until the contract was completed.
A Panel member noted the mitigations put in place for infrastructure and building works, which included measures to avoid reducing access for existing business. Officers were asked if there were any issues causing delays, such as the change in partners for the Holy Trinity project. The Deputy Chief Executive explained that there was an interactive map on the Council’s website to show the latest information on each project. Coordinating between partners had always been recognised as a challenge, and mitigations were needed to minimise effects on residents and businesses whilst work was carried out. Funding had been put together to recruit a coordinator to manage scheduling of projects. This officer had access to Council work plans and worked with partners such as the Business Improvement District, to keep businesses informed.
It was confirmed that there had been a delay caused by the ending of the partnership with C360 over Holy Trinity, and the tendering for a new partner. Work could now proceed with the new partner. Working with the Police, the Council sought to introduce features to schemes like Holy Trinity that would minimise crime and antisocial behaviour.
Planning for the introduction of kerb-less streets in some areas were raised, with concerns that the quality of some existing pavements was poor and needed improving. The Leader noted that some parts of the City centre had seen mending of its poor paving. The Council and County Council were investing in mending more, including in parts such as North Station Road and the bridge at Middleborough. The Head of Economic Growth explained that kerb-less street work had not proceeded as lessons had been learned from the situation at St Nicholas Square. Officers were mindful of optimism bias, and costs had escalated due to unforeseeable factors. such as the war in Ukraine. Some of the complexities of the St Nicholas Square project included archaeology, highways issues and utilities work. Lessons learned would be circulated to all councillors.
A Panel member asked what the original target dates had been for projects, and by how much any of these had slipped. Officers were also asked for examples of lessons learned that would improve future bids. The Deputy Chief Executive underlined that the Town Deal timeline had always run to 2026, adding that two years had been given on the Levelling Up Fund project work. Original dates had varied from project to project. Some were on time whilst others, such as St Nicholas Square, had slipped. The Heart of Greenstead project had always been planned for completion near the end of the programme. Delivery and timings would be examined, to provide lessons. The Head of Economic Growth noted that lessons had already been learned, and that project timescales were, by necessity, estimates. The Council aimed to be pragmatic, but not all factors were within its control.
A Panel member urged consideration as to why work was being done, giving the £6m of work in Greenstead as being focused on the area due to the local multiple factors of deprivation. A request was made for estimated impacts that the Heart of Greenstead project was expected to have, and as to which indices of deprivation were expected to lessen over the next five years. Concern was raised that, if outcomes could not be estimated, there was a risk that the investment would be wasted. Officers were asked how the economic prosperity of Greenstead could be raised, and whether this would be part of the planning process. The Deputy Chief Executive gave assurance that the impacts would be significant. Benefits to be realised had been laid out in the Town Deal plans. Place planning in Greenstead included improvements in health for residents. Metrics and evaluations would be included, and Rory Doyle, Strategic Director, was working with the University on evaluation of the impact.
The Deputy Chief Executive was asked whether a Health and Wellbeing Board would have oversight of health work, if such a Board was formed. A Panel member asked if the Panel should book items into its 2025-26 work programme to obtain information on ongoing project work, and possibly include work by the University of Essex to evaluate likely outcomes and impacts. The Deputy Chief Executive informed the Panel that two bits of evaluation work were already being discussed with the University, which was interested in research projects in the area such as this. More details of oversight of aims would be known once the Health and Wellbeing Board was in place.
A concern was raised that there was no detail given as to management resource put into the project work by the Council, such as time given by officers and management, and by officers of partner organisations. A request was made for an estimate of the amount of work being put in by officers, and the time it took out of their working. The Deputy Chief Executive explained that some project capacity could be charged to the relevant projects. Regarding management time, the Deputy Chief Executive estimated that around a fifth of her working time was spent on matters regarding the Town Deal, Levelling Up Fund projects and the City centre. Much time was put in by officers, politicians and Town Deal Board members. The Head of Economic Growth added that the approach had been for a lean operation, and that overall, there had not been a huge management resource devoted to these projects. From the Town Deal fund a Programme Manager post had been created, along with a part-time Engagement Specialist.
RESOLVED that the SCRUTINY PANEL receives a briefing note to lay out the scale of management resource being assigned to Town Deal and Levelling Up Fund project work.