305
The Place Strategy Manager presented the report to the Committee detailing that Officers and consultants had worked to inform the potential spatial options which may be appropriate for the strategy for growth up to 2041. The Committee heard that the report contained details in paragraph 5 regarding the terms of the plan and the establishing method expressed as a number per year of the housing need figure. It was noted that the transition arrangements from the previous local plan detailed that the Housing need per annum was 920 and that for the local plan review this needed to be updated using the standard methodology. The Committee heard that the expectation of the updated number was that the number would be 1043 houses per annum and that there was no expectation that Colchester would be considered for an exception taking into account the Strategic Land Availability Assessment. It was detailed that the appropriate spatial strategy would be put forward for a consultation leading to a preferred strategy and settlement hierarchy and asked the Committee to note the emerging Local Housing need figure for the Local Plan Review covering the period up to 2041.
In response to a question from the Committee the Joint Head of Planning responded that the re-introduction of West Tey was not a decision that was before the Committee.
Members discussed the role of the Objectively Assessed Need (OAN) and the role of the infrastructure Audit that needed to be completed by the end of the Autumn, the challenges around the A1120 around Marks Tey, the current state of the Rapid Transport System (RTS) and how much weight could be given to this whilst noting that the funding had not been allocated yet and that the A12 upgrades had not started yet.
The Place Strategy Manager responded that the Infrastructure Audit was being undertaken by AECOM who were working to deliver the results in time for the plan making process which would form part of the evidence base. The Joint Head of Planning added that the Infrastructure Audit would inform the plan but that it was a two-stage approach whereby the baseline would be looked at as well as what was needed beyond that. The Committee heard that the Council was reliant on National Highways to provide upgrades to the A1120 and the A12 and that it would be important to engage with them to understand what was possible bearing in mind the history of the road improvements. The Committee heard that the developer could forward fund the RTS and that if this was needed from the beginning then this could be agreed through a Section 106 Agreement following on from a consultations with National Highways and Essex County Council’s Highways Department
Members continued to discuss the report with issues being raised regarding the confidence in the number of Houses being built per annum, the spatial strategy and its proposed finalisation and agreement, and the current status of Middlewick as a site.
The Place Strategy Manager and Joint Head of Planning responded that the housing number per annum was based off of evidence and would run until 2041 and that it would be reviewed every 5 years. It was detailed that the preferred options for the Local Plan and the spatial strategy would be consulted on and confirmed that Middlewick’ status was currently as an adopted site. It was noted that the Housing number could vary between the meeting and the adoption process which could be based off of National changes as well as evidence gathered.
The debate continued with Members discussing issues including: the impact upon the TCBGJC and how this would affect the road links and the RTS. In response to the points raised regarding the TCBGJC the Place Strategy Manager detailed that the housing numbers would be dependent on the evidence provided and outlined that they understood the concerns regarding the TCBGJC and where any additions to this would be placed but confirmed that exceptional circumstances could be taken into account however as referenced in the report these were very limited and Colchester would be unlikely to qualify for these. The Joint Head of Planning added that the RTS was not reliant on developer funding but it could be given priority if required and that nothing at this stage had been ruled in out of the process but that the process would help inform the settlement boundary review.
The debate continued with Members discussing that they were pleased to see Aecom undertaking the Infrastructure Audit and that it was hoped that this would bring attention to some of the infrastructure issues. Some Members detailed their frustration at the current situation whereby infrastructure problems could not be currently solved through the Section 106 framework but concluded that the additional briefings on the Local Plan review were welcomed.
In response to questions from the Committee the Place Strategy Manager and Joint Head of Planning detailed that the items being considered in the infrastructure audit were appropriate to informing the Local Plan review and would inform the evidence base regarding the final housing number. In response to a further question the Committee heard that the Council did not have the funding to introduce design codes and that Colchester did not have strong grounds to bid for additional funding.
The Committee discussed the Standard Methodology and requested further information on how this was calculated and queried whether this took into account age profiles as well as rural wards where the demographics are significantly different as well as how the transient student population of the city would affect this as well as that of Tendring’s population.
The Joint Head of Planning detailed that the they would circulate guidance to Members on how the standard methodology works and clarified that if there was the evidence to challenge the annual housing number then that would be undertaken but warned Members that evidence would be needed for any challenge on this as the bar was set very high. It was detailed that the Housing needs study would be circulated once it had been completed. Further to this it was detailed that the evidence would be provide details of demographics including students and the elderly residents in the City and their housing needs in the Council’s area. The Joint Head of Planning concluded by detailing that the Tendring District Council had not completed their review and did not have a new Housing Number yet.
Members continued to discuss the report on issues including the Hythe area and flooding issues that pervaded the area which dated back to the 1960s with concern being raised that further development in the area could exacerbate the flooding issues.
The Place Strategy Manager responded that the flooding issues would be taken into account. The Place Strategy Manager responded to further questions from the Committee outlining that the Council would be consulting with the neighbouring authorities and that if the Garden Community could not be delivered then the housing on that site would need to be found elsewhere.
A short break was taken between 19:30-19:40.
In response to further questions the Place Strategy Manager and Joint Head of Planning detailed that the figure of 920 dwellings per annum was the previous number of dwellings per annum that needed to be built as part of the transitional arrangements however the method that was used last time has changed to the Standard Methodology.
It was proposed and seconded that the report be accepted as detailed in the officer recommendation with an addition to 2.1 that the Committee noted the emerging housing need whilst acknowledging that it would be subject to change as further evidence became available.
RESOLVED (EIGHT votes FOR and ZERO votes AGAINST with ONE ABSTENTION) that:
The Committee noted the emerging housing need whilst acknowledging that it would be subject to change as further evidence became available covering the period up to 2041.
And
The Committee noted the spatial approaches and spatial options set out in paras 5.19-5.41 of the report which are to be tested by the relevant evidence to inform the consideration and drafting of the preferred options Local Plan Review.