318
Councillor Dave Harris addressed the Committee as a visiting Councillor. The speaker thanked the Officers for their work on the review and detailed that the Council was in the middle of the review process and commented on the Colchester Gazette article detailing that Natural England would be working with the Council and that there were indications that the Middlewick area would be protected. The speaker concluded by asking how this relationship with Natural England would be maintained going forward and what input they would have.
At the request of the Chair the Place Strategy Manager detailed that the Council would be accepting Natural England’s offer to review the evidence and that the collaborative working would be continuing into the next stage of the Local Plan process where their offer would be reviewed.
In response to the Officer Councillor Harris queried how the housing that was allocated to Middlewick would be accommodated instead of on the site.
In response to Cllr Harris the Place Strategy Manager detailed that the Local Plan Review would take into account the whole City area and that would be considered in an evidence-based approach.
Councillor Martyn Warnes addressed the Committee as a visiting Councillor. The speaker detailed that Berechurch did not have a dedicated Community Centre and instead there were numerous Church Halls. It was requested that this was reviewed so that the community needs could understood and met in the future. The Committee heard that there were improvements that could be made to the rail network specifically with regards to the Colchester Town station which would work alongside the Councils Climate Emergency declaration. Councillor Warnes concluded by detailing that the requirements for Middlewick should be measured against the core principles to achieve a biodiversity net gain and minimise the adverse effects on the land.
At the request of the Chair the Joint Head of Planning responded that the improvements at the Colchester Town Station could be looked into further and that the concerns regarding the community facilities in the Berechurch area were noted and will ask the Community Development team to get in touch so that these concerns could be factored in.
In response to the Officers, Councillor Warnes queried whether there were any requests for facilities that had yet to be accepted.
The Joint Head of Planning detailed that some projects had been put forward but were not acceptable in planning terms due to the statutory tests necessary for making the applications and projects acceptable.
Sandra Scott, Place Strategy Manager, presented the application to the Committee noting that it was appreciated that there were a large number of lengthy documents as well as technical reports detailing factual evidence. The Committee heard that the Local Housing needs assessment considered the overall need of the different groups in Colchester which worked out to be 1300 dwellings per annum. This assessment had been based on the current and future housing needs and included the mix, tenure split and the range of specialist housing needs as well as Gypsy and Traveller sites. It was noted that these were identified in appendix B which identified the overall need until 2041.
The Committee heard that the Infrastructure Audit and delivery plan key points were summarised in 5.20-5.26 of the report and that they identified the growth for the Local Plan period and confirmed that this would form part of the evidence base once it was published. It was noted that there were 37 different types of infrastructure that would be included in the report as well as a planned baseline position, where there were supply gaps, and the inclusion of stakeholder engagement which would inform stages 1 and 2 of the report. This would be considered with the mitigation requirements and retail and leisure study and commercial leisure sectors whose key points were included at 5.27-5.33 of the report. These looked at all the separate centres within Colchester regardless of scale and identifying the appropriate change and viability of functions whilst providing health checks. The report also included details of the Landscape assessments providing an up-to-date evidence base which would inform the baseline. It was detailed that the Strategic Land Availability Assessment was detailed within the report at 5.42 and confirmed that the methodology had been agreed in the previous year. Through this stage one assessment it had been found that 72% of those identified were suitable and details of these specific sites were detailed in appendix 1. The Place Strategy Manager concluded by detailing that as more information became available then this would be published and that the recommendation was to note the progress made on the evidence base and note the publication of the completed evidence documents referred to in section 5 of the report.
The Committee debated the report and raised questions regarding the infrastructure audit and detailed that there was concern regarding sewage capacity that would be included in the Water Cycle Study and how this would be looked at in terms of growth options being proposed and queried how this would be shown in the recommended plan.
At the request of the Chair, The Place Strategy Manager detailed that the evidence needed to be fully tested to understand the implications of the plan as the Water Cycle Study was only one part of the wider evidence base. It was confirmed that the water and sewage element would be included within the water cycle study which would be a statement at a point in time but would be looking at growth and the challenges thereafter. In response to a further question from the Committee the Place Strategy Manager confirmed that the Housing Numbers in the NPPF could not be delayed due to a lack of infrastructure.
In response to a question from the Committee the Place Strategy Manager confirmed that the report on Middlewick was expected in the upcoming week and confirmed that once this was available it would be published on the website.
Members debated the report on issues including: that the evidence base was a starting point which could be used as a guide for infrastructure through Section 106, CIL and wider government funding, especially as the A120 was a challenge in every option. Marks Tey was noted as requiring major investment to support the plan going forward as well as other utilities including wastewater and electricity in more rural areas such as Tiptree and Copford.
With regard to retail the report on retail and leisure trends and predicted supply and demand were noted. The landscape character assessment was described and confirmed it would help inform potential impacts from development proposals.
Members continued to debate the report on issues including: when the water cycle study would be completed, that the Government had promised the building of new reservoirs and queried whether they were considering one in the Colchester Area as it was projected there would be significant population growth. On page 592 the Committee queried the spare sewage capacity and detailed that West Mersea had been promised an upgrade that had not happened and currently meant that 3-4 tankers a day were removing waste and had meant that residents in East Mersea had not been able to sit in their back gardens because of the smell. Further to this it was detailed that there had been a 20cm rise in sea level since the 1953 floods and the land was sinking at a rate of 0.8mm a year leading to a more likely 1 in 10-year flood event.
At the request of the Chair the Place Strategy Manager responded that these points raised regarding flooding would be taken up with the consultants and the water cycle study would be available before the plans publication but could not confirm a definitive time on this and detailed that they were not aware of any conversations regarding new reservoirs.
Members discussed the measuring of average income per household and how on West Mersea this was below the normal average due to more than one third of the population being retired which was twice the national average and as such this was interpreted that residents couldn’t afford properties. It was queried whether this was the case in other wards.
At the request of the Chair the Place Strategy manager responded that they did not have the specialist knowledge with regards to the methodology regarding this scenario but accepted that there were certain factors that were skewing the relationship between income and home ownership however it was detailed that this would be set out in the guidance to follow. With regards to the question of where people had moved from to areas such as West Mersea the Council relied upon input from those contacted and if this information was not provided then it couldn’t be recorded.
In response to the Have Your Say Speaker earlier in the meeting the Joint Head of Planning clarified that further that the Council’s scheme of delegation for planning applications was held up as best practice to other Councils when conducting peer reviews and detailed that this would be sent round to all Members.
A short break was taken between 19:30 and 19:40.
Members queried p93 of the report where it detailed that 21,400 additional jobs would be created and whether this was in construction or lifetime of the plan. Further to this it was questioned whether the 877 additional affordable homes as listed on page 93 were in addition to current stock or included it.
At the request of the Chair the Place Strategy Manager responded that the figure of 21,400 jobs was looking at the calculation and population and what that could support as a crude calculation and detailed that there would be an employment land needs assessment. With regard to the Affordable Housing this was confirmed as being additional to current stock and it was recognised that this would not all be developed but that the Council would be securing the maximum going forward and of the right mix with the starting point being the policies in the Local Plan.
Concern was raised that the proposed number of affordable homes would not meet the needs of the community and could lead to more people living in Housing Association’s properties. Members discussed how the delivered dwellings total of 1098 and how a large number of these came from the University of Essex. It was queried if the University had not built the student accommodation whether the Council would have missed its housing target and how that number could be included in the numbers as it was not a formal dwelling.
The Joint Head of Planning confirmed that the Council would have missed the target if they had not been completed and detailed that the student accommodation flats were not considered a dwelling on a 1-1 base but that 2.46 student flats counted as 1 dwelling in the housing target.
Points were made regarding the long-term plans to ensure future generations using services in Colchester rather than further away and plans to improve transport to employment hubs. The Joint Head of Planning said that retaining affordable homes was key and detailed that there were plans to reform the Right to Buy housing scheme.
Members questioned whether the university accommodation had been delivered in one year and that there was concern regarding infrastructure in the rural parts of the City area including phone signal and how the proposals from National Grid were not shown in the documentation.
The Joint Head of Planning and Place Strategy Manager responded that the council monitored the completions of developments and that this had been completed in time for the relevant term. It was detailed that the infrastructure work said that more could be done for phone signal improvement and confirmed that there was not a reference to pylons in the information before the Committee.
Members questioned the use of “low income” in the report with regards to housing and how this was defined.
At the request of the Chair the Joint Head of Planning responded that the use of “low income” was a Government definition which disregarded all other factors as it was a benchmark level identified for the area.
Members debated the information noting that the Council had benefitted from the very high-density development at the University but this could not be relied upon again. Members discussed the table on p184 of the agenda regarding the proportion of people who were able to rent and buy property whilst living in the Private Rented sector. It was discussed that the table did display people who could buy and rent and showed that in the future people will not be able to rent or buy as detailed in the Council Tax support scheme. It was detailed that the Right to Buy discount had been returned to the pre 2012 levels and meant that there was an effective 14% discount. As such this meant that less people would be buying their homes and there would be no need to replace the ones that would have been bought. However, this was noted to also mean that the Council had less income to put into new homes and some of them were no longer viable and there was further work to be done. The debate concluded with it being noted that there had been a surge in fraudulent requests for the Right to Buy scheme.
RESOLVED (UNANIMOUSLY) That the Local Plan Committee noted the progress made on the evidence base to support the Colchester Local Plan Review and the publication of the completed evidence documents referred to in section 5 of the report.